2016 |
Replacement of the Oil Metering Facilities with associated works at ES Sider Terminal |
|
Libya |
Waha Oil Company (Ex Oasis Oil Company) |
|
2016 |
Maintenance of 500 M3 Light Fuel Oil Tankwith Related Facilities and Fire Fighting System at Mitiga Power Plant |
|
Libya |
GECOL - General electricity Compnay of Lybia |
|
2016 |
Gialo Water Disposal System |
Gialo Oilfield |
Libya |
Waha Oil Company (Ex Oasis Oil Company) |
|
2014 |
The replacement/installation of liner at Evaporation Pond at Ras Lanuf Export Terminal |
Ras Lanuf Tank Farm |
Libya |
Harouge (VEBA) Oil OperationsB.V. Libyan Branch |
|
2012 |
Cooling system piping alternation for Tanks 210 CT1/2, BT1, NT1/2, KT4/5/6, GT9/10/11/12 / ST1/2/3/4 |
Ras Lanuf |
Libya |
LERCO – Libyan Emirates RefineryCompany |
|
2012 |
Alternative tank for storing kerosene products; Contract No. 0627 |
Ras Lanuf |
Libya |
LERCO – Libyan Emirates RefineryCompany |
|
2010 |
Dahab Highline to Feed NewProduction Wells PN 1222A; (11 km new 34.5 KV highline) |
Zuetina Oil Terminal |
Libya |
ZUEITINA Oil Company |
|
2010 |
Power Supply for 2 CathodicProtection Stations |
Zuetina Oil Terminal |
Libya |
ZUEITINA Oil Company |
|
2010 |
Sea Water Intake: Replacement of8” Hypochlorite Lines and Maintenance of 144” SWI Pipes |
Ras Lanuf |
Libya |
RASCO - Ras Lanuf Oil &GasProcessing Company, Inc. |
|
2010 |
AGOCO Tobruk - Installation ofFoam Extinguishing System on Tanks 805 & 842 and Fire Protection Systemon the Floating Roof Tanks at Tobruk Refinery Project K-52 |
Tobruk |
Libya |
AGOCO - Arabian Gulf Oil Company |
|
2010 |
Supply and Installation of 15/30kV Tank Farm/Terminal Feeder Cables and Tank Farm Switchgears; Contract No.2008-39 + CO – Main Power Supply 5 MVA TS (30 /12.5 kV) at Tank Farm forentire HOO R/L. |
Ras Lanuf Oil Terminal |
Libya |
Harouge (VEBA) Oil OperationsB.V. Libyan Branch |
Engineering, design, supply andinstallation of 15/30 kV Tank Farm/Terminal Feeder Cablesand Tank Farm Switchgears |
2010 |
Replace Main Distribution Board; Ras Lanuf Terminal;
– SERVICE ORDERNo. 1- Terminal MV Underground Cables |
Ras Lanuf Oil Terminal |
Libya |
Harouge (VEBA) Oil Operations B.V. Libyan Branch |
Replacement of Main Distribution board at Ras Lanuf Terminal |
2010 |
Cleaning and Refurbishment Oil Tank 2100-GT-11
|
Ras Lanuf
|
Libya
|
LERCO – Libyan Emirates Oil Refining Company
|
Emptying, Cleaning and Refurbishment of Heavy Gas Oil Tank 2100-GT-11
|
2009 |
General Reconstruction Of Main Facilities For Liquid Fuel Transfer From Ground To Oil River Barge |
Oil Refinery Bosanski Brod
|
Bosnia & Hercegovina
|
Zarubezneftestrojmontaz O.O.O. Moskva, Russia & Oil Refinery Bosanski Brod, Bosnia & Hercegovina
|
Design, Engineering & Construction Of Pipe Lines Transfer Sistem, Custodi Transfer Metering Skids, Firefighting Sistem, Oil Barge On River Sava Including Conection Between.
|
2009
|
Cleaning of HC111
|
Nafura
|
Libya
|
WINTERSHALL Libyan Branch
|
Cleaningof HC 111 exchange unit with high pressure pump.
|
2009
|
Installation of fire fightingsystem
|
Tobruk
|
Libya
|
Arabian Gulf Oil Co.
|
Installation of foamextinguishing system on tanks and fire protection systemon floating roof tank
|
2009
|
Upgrade of MV switchgear relayprotection system
|
Oil field 103A & 103B
|
Libya
|
Zueitina OilCo. Libya
|
Installation of MV switchgearrelay protection system and monitoring control equipment.
|
2009
|
Works on underground facilitiesat Tank Farm
|
Ras Lanuf
|
Libya
|
Harouge Oil Operations
|
Maintenance and servicing ofunderground facilities.
|
2008
|
Dahab highline
|
Zueitina
|
Libya
|
Zueitina OilCo. Libya
|
Engineering and installation ofMW power supply (9km new 34,5 KV high line)to feed eight new productionwells.
|
2008
|
Main Distribution Board, RasLanuf Terminal - Replacement
|
Ras Lanuf
|
Libya
|
Harouge Oil Operations
|
Supply and Installation of15/30kV Tank Farm/Terminal Feeder Cables and Tank Farm switchgears.
|
2007
|
Ethylene plant 8th turnaround
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Turnaround services, instrumentand NDT insp. specialist .
|
2007
|
Glass reinforced pipesreplacement
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Glass reinforced pipesreplacement
|
2007
|
LPG plant terminal
|
Zueitina
|
Libya
|
Zueitina OilCo. Libya
|
Turnaround services, instrumentspecialist, pipe line specialist.
|
2007
|
Maintenance of the facilities atAmal field
|
Amal Field
|
Libya
|
Arabian Gulf Oil Co.
|
Construction works andengineering; supply of material.
|
2007
|
Polyethylene plant 3rdturnaround
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Overhauling of rotary equipment,engaged 35 specialists.
|
2007
|
Replacement of main distributionboard
|
Ras Lanuf
|
Libya
|
VebaOil Co. Libya
|
Replacement of main distributionboard, installation of new equipment.
|
2006
|
Construction of a new fire watertank
|
Sahabi Field
|
Libya
|
Arabian Gulf Oil Co.
|
Main design and construction ofa 5000 BBLS tank.
|
2006
|
Reconstruction of oil tank
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Re-bottoming and annular Ringreconstruction.
|
2005
|
Cleaning and refurbishment offuel oil tank
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Cleaning and refurbishment offuel oil tank.
|
2005
|
Dry Slop Oil tank
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Re-bottoming and annular platesreplacement.
|
2005
|
Installation of Runway Lightingsystem , Ed Dib Airport
|
Ghani Field
|
Libya
|
VebaOil Co. Libya
|
Main design, completeconstruction and start up, Fire detection system installation.
|
2005
|
Pump stations
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Servicing of pump stations.
|
2004
|
Ethylene plant 7th turnaround
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Provision of 239 highly skill;mechanics, rotating equipment and instrumentation specialist, pipe fitters,welders and NDT inspectors.
|
2004
|
Polyethylene Plant 2ndturnaround
|
Ras Lanuf
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Overhauling of mechanical,electrical & instrumentation equipment and inspection. 55 highlyspecialized technicians engaged
|
2002
|
Operation and maintenanceservices at oil fields & terminal
|
Multiple Sites
|
Libya
|
Zueitina OilCo. Libya
|
Technical assistance servicesfor operation and maintenance.
|
2002
|
Shurtan project
|
Karshi
|
Uzbekistan
|
AbbLumus Global, USA
|
Management and processsupervising services for ethylene & polyethylene plant and utility.
|
2001
|
Operation services atPolyethylene plant & polymer handling
|
Film plant
|
Libya
|
Ras Lanuf Oil & GasProcessing Co. Inc
|
Technical assistance servicesfor operation.
|
1999
|
Maintenance services at oilfields in association with Energoinvest Co.
|
Multiple Sites
|
Libya
|
Arabian Gulf Oil Co.
|
Technical assistance servicesfor maintenance.
|
1998
|
FCC plant
|
Plock
|
Poland
|
Technipetrol,Plock, Poland and I.C.R.I. s.p.a., Rome Italy
|
Commissioning of instrumentationand process start-up of FCC plant.
|
1998
|
Oil refineries and Petrochemicalcomplex
|
Port Harcourt
|
Nigeria
|
Comerintltd., Nigeria
|
Mechanical maintenance services.
|
1997
|
Ammonia plant
|
Urumqui
|
China
|
Technimont s.p.a. Italy and E.C.O.S. Ltd., England
|
Commissioning start-up and process back-up services.
|
1997
|
Polypropylene plant
|
Ufa
|
Russia
|
Technimont pp, Ufa Russia and I.C.R.I. s.p.a., Rome, Italy
|
Instrumentation back- up services.
|
1996
|
Ethylene plant
|
Canton
|
China
|
Technimont s.p.a. and I.C.R.I. s.p.a., Rome, Italy
|
Commissioning of instrumentation including DCS and software programming, process start-up, initial operation and back-up of instrumentation and operation services.
|
1996
|
Fibrex S.A. H2 and Co2 plant Fibrex S.A. H2 and Co2 plant
|
Piatru Niemc
|
Romania
|
Kinetics Technology International s.p.a., Rome, Italy and WTI, Ireland
|
NDT equipment inspection.
|
1996
|
Petrochemical plant
|
Al Shuaiba
|
Kuwait
|
Kinetics Technology International s.p.a., Rome, Italy and WTI, Ireland
|
Construction and commissioning of plant's Furnaces section
|
1996
|
Polypropylene plant
|
Dalian
|
China
|
Technimont s.p.a. and I.C.R.I. s.p.a., Rome, Italy
|
Commissioning of instrumentation including DCS and software programming, process start-up, initial operationand back-up of instrumentation and operation services.
|
1996
|
Power plant
|
Omar
|
Syria
|
Technipetrol s.p.a,. Rome, Italy and I.C.R.I s.p.a., Rome, Italy
|
Classroom and on job training of client's electrical staff.
|
1996
|
Power plant
|
Omar
|
Syria
|
Technipetrol s.p.a., Rome, Italy and I.C.R.I s.p.a., Rome, Italy
|
Commissioning, start-up and back-up of mechanical and electrical services.
|
1996
|
Steel Factory
|
?
|
Thailand
|
Daneco s.p.a. and I.C.R.I s.p.a., Rome, Italy
|
LV electric supervision and SIMATIC software programming.
|