New camp established at Zuetina field Fida, the complete mobilization of equipment finished and works on laying cables have begun.

This new camp has a capacity of 19 beds and it is fully equipped with following facilities: kitchen, generator room and sleeping trailers.

Trencher has already dag 1km of soil and it is expected that 2, 1 km of cable will be put in place by the end of next week.

This project consists of powering 8 wells and laying 11km of HV cables.